Progress Day care centre

Dear sponsors,

The early started winter is getting colder and colder in Sarangkot, especially in the morning and in the evening!
The workers are busy to make the walls. They also fixed the doors and windows at the first floor. Down floor the inside walls are still not plastered.
Every work is getting late because of not enough workers. Our contractor could not get workers there because it is in the mountains and they have to expense a lot of their money to get people to work. The villager workers could not fit with the outer group of workers, because they are less qualified. Another problem starting is lack of water. The water sources are slowly getting dry because of the winter season.

At the moment they are preparing to fix the iron grid of the second floor. The second floor will be cemented soon, says the contractor!
The little toddlers of our DCC are waiting to get back their comfort!

Thank you so much for your support!

Sabine & Ram Chandra Sharma
Chairman QOLN

Front side of the day care centreFront side of the day care centre

Back side of the day care centreBack side of the day care centre

Day care centre toddlers are having a look at the progress madeDay care centre toddlers are having a look at the progress made

Day care centre toddlers are having a look at the progress madeDay care centre toddlers are having a look at the progress made